Abstract:
The determination of optimal fleet is key activity in mining operation as loading and haulage
account to more than 60% of total operation cost. One of the major costs in mine is related to the
purchase and application of equipment. Proper fleet selection, in a way that secures the
production needs of a mine as well as minimizing the cost of production, is one of the main
challenges of mine planners. The equipment selection process can be classified into three phases
i.e. type of fleet, size of equipment, and calculation of required numbers. This study focuses on
the proper placement of the passing bays in an underground tunnel that optimizes production
efficiency, and meets the desired output from the available working-time which can also be
referred to as the time factor. This is achieved by helping in the determination of a satisfactory
cycle time that will conform with the continuous functioning of the loader, which leads to the
design of a fleet system that will be perfect for a shovel from the inequality CYTMIN ≤ NT (Tl +
Ts). This implies that the circle time must be less than or equal to the number of trucks multiplied
by the summation of the loading time and the spotting time. This also means that the loader
should at no time during the loading and haulage operation await other trucks. When selection of
equipment is not properly done it results into over trucking or under-trucking. In many
underground mines, haulage vehicles carry ore from underground loading stations to the surface.
Vehicles travel in narrow tunnels with occasional passing bays that allow descending empty
vehicles to pull off the main path and wait for ascending laden vehicles to pass. The number of
passing bays and their locations influence the delays to descending vehicles, and hence the
haulage productivity of the mine. formulate and solve a mixed integer programming (MIP)
model to determine the optimal locations of passing bays to maximize haulage productivity for
given numbers of vehicles and passing bays. The loading and hauling system at Wagagai mine
need to be evaluated since the operations are expanding and new equipment (trucks and shovels)
has been introduced. With the increase in the number of units for both excavation and
transportation, the mine aims to operate at maximum efficiency. The key contribution of this
paper is to find the optimal locations of passing bays and the associated vehicle schedule to
maximize tonnes hauled per shift in an underground mine.